Capacity curtailment for the IFA ( FR<>GB) for the delivery day 09/02/2022
Dear Market Participants,
Please find a curtailment notice for the 9th Feb 2022 for IFA and publish this to the message board. Thanks.
FR>GB
- TSO(s) *:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA FR>GB
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period :
09/02/2022
00:00 - 01:00 |
1000 |
01:00 - 02:00 |
1000 |
02:00 - 03:00 |
1000 |
03:00 - 04:00 |
1000 |
04:00 - 05:00 |
1000 |
05:00 - 06:00 |
1000 |
06:00 - 07:00 |
1000 |
07:00 - 08:00 |
1000 |
08:00 - 09:00 |
1000 |
09:00 - 10:00 |
1000 |
10:00 - 11:00 |
1000 |
11:00 - 12:00 |
1000 |
12:00 - 13:00 |
1000 |
13:00 - 14:00 |
1000 |
14:00 - 15:00 |
1000 |
15:00 - 16:00 |
1000 |
16:00 - 17:00 |
1000 |
17:00 - 18:00 |
1000 |
18:00 - 19:00 |
1000 |
19:00 - 20:00 |
1000 |
20:00 - 21:00 |
1000 |
21:00 - 22:00 |
1000 |
22:00 - 23:00 |
1000 |
23:00 - 00:00 |
1000 |
- Amount of LTTR remaining after curtailment :
09/02/2022
00:00 - 01:00 |
500 |
01:00 - 02:00 |
500 |
02:00 - 03:00 |
500 |
03:00 - 04:00 |
500 |
04:00 - 05:00 |
500 |
05:00 - 06:00 |
500 |
06:00 - 07:00 |
500 |
07:00 - 08:00 |
500 |
08:00 - 09:00 |
500 |
09:00 - 10:00 |
500 |
10:00 - 11:00 |
500 |
11:00 - 12:00 |
500 |
12:00 - 13:00 |
500 |
13:00 - 14:00 |
500 |
14:00 - 15:00 |
500 |
15:00 - 16:00 |
500 |
16:00 - 17:00 |
500 |
17:00 - 18:00 |
500 |
18:00 - 19:00 |
500 |
19:00 - 20:00 |
500 |
20:00 - 21:00 |
500 |
21:00 - 22:00 |
500 |
22:00 - 23:00 |
500 |
23:00 - 00:00 |
500 |
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Capacity limitation due to unplanned maintenance
GB > FR
- TSO(s) *:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA GB>FR
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period:
09/02/2022
00:00 - 01:00 |
1000 |
01:00 - 02:00 |
1000 |
02:00 - 03:00 |
1000 |
03:00 - 04:00 |
1000 |
04:00 - 05:00 |
1000 |
05:00 - 06:00 |
1000 |
06:00 - 07:00 |
1000 |
07:00 - 08:00 |
1000 |
08:00 - 09:00 |
1000 |
09:00 - 10:00 |
1000 |
10:00 - 11:00 |
1000 |
11:00 - 12:00 |
1000 |
12:00 - 13:00 |
1000 |
13:00 - 14:00 |
1000 |
14:00 - 15:00 |
1000 |
15:00 - 16:00 |
1000 |
16:00 - 17:00 |
1000 |
17:00 - 18:00 |
1000 |
18:00 - 19:00 |
1000 |
19:00 - 20:00 |
1000 |
20:00 - 21:00 |
1000 |
21:00 - 22:00 |
1000 |
22:00 - 23:00 |
1000 |
23:00 - 00:00 |
1000 |
- Amount of LTTR remaining after curtailment:
09/02/22
00:00 - 01:00 |
500 |
01:00 - 02:00 |
500 |
02:00 - 03:00 |
500 |
03:00 - 04:00 |
500 |
04:00 - 05:00 |
500 |
05:00 - 06:00 |
500 |
06:00 - 07:00 |
500 |
07:00 - 08:00 |
500 |
08:00 - 09:00 |
500 |
09:00 - 10:00 |
500 |
10:00 - 11:00 |
500 |
11:00 - 12:00 |
500 |
12:00 - 13:00 |
500 |
13:00 - 14:00 |
500 |
14:00 - 15:00 |
500 |
15:00 - 16:00 |
500 |
16:00 - 17:00 |
500 |
17:00 - 18:00 |
500 |
18:00 - 19:00 |
500 |
19:00 - 20:00 |
500 |
20:00 - 21:00 |
500 |
21:00 - 22:00 |
500 |
22:00 - 23:00 |
500 |
23:00 - 00:00 |
500 |
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Capacity limitation due to unplanned maintenance