Ramping limit reduction for NordLink
Published:
Dear Market Participant,
Statnett and TenneT DE has decided to set the ramping limit to 300 MW on NordLink from the start of go-live 08.12.2020.
The reduction to 300 MW (from the earlier published 600 MW) is due to operational security on the Statnett side of NordLink.
During the first months of operation Statnett will monitor the operational impact of the 300 MW limit to the Norwegian Power System, and with additional measures seek to increase this limit up to the maximum limit of 600 MW.
Any change from the 300 MW limit will be published in due time.
Best regards,
JAO Operations Team, on behalf of Statnett and TenneT DE