Capacity Curtailment on the AT-IT and SI-IT borders for delivery day 30/03/2020

Published:

TSO(s) *:

TERNA

Identification of affected Long Term Transmission Rights

Austria to Italy

Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

Affected volume in MW / hour for each concerned period :

Austria to Italy

30/03/2020

00:00 – 01:00 178 MW

01:00 – 02:00 178 MW

02:00 – 03:00 178 MW

03:00 – 04:00 178 MW

04:00 – 05:00 178 MW

05:00 – 06:00 178 MW

06:00 – 07:00 178 MW

07:00 – 08:00 178 MW

08:00 – 09:00 178 MW

09:00 – 10:00 178 MW

10:00 – 11:00 178 MW

11:00 – 12:00 178 MW

12:00 – 13:00 178 MW

13:00 – 14:00 178 MW

14:00 – 15:00 178 MW

15:00 – 16:00 178 MW

16:00 – 17:00 178 MW

17:00 – 18:00 178 MW

18:00 – 19:00 178 MW

19:00 – 20:00 178 MW

20:00 – 21:00 178 MW

21:00 – 22:00 178 MW

22:00 – 23:00 178 MW

Amount of LTTR remaining after curtailment :

Austria to Italy

30/03/2020

00:00 – 01:00 86 MW

01:00 – 02:00 86 MW

02:00 – 03:00 86 MW

03:00 – 04:00 86 MW

04:00 – 05:00 119 MW

05:00 – 06:00 119 MW

06:00 – 07:00 116 MW

07:00 – 08:00 116 MW

08:00 – 09:00 116 MW

09:00 – 10:00 124 MW

10:00 – 11:00 124 MW

11:00 – 12:00 124 MW

12:00 – 13:00 124 MW

13:00 – 14:00 124 MW

14:00 – 15:00 124 MW

15:00 – 16:00 124 MW

16:00 – 17:00 157 MW

17:00 – 18:00 157 MW

18:00 – 19:00 157 MW

19:00 – 20:00 157 MW

20:00 – 21:00 157 MW

21:00 – 22:00 157 MW

22:00 – 23:00 157 MW

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Voltage stability issue on the Italian Electrical system.

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

-------------------------------///----------------------------

TSO(s) *:

TERNA

Identification of affected Long Term Transmission Rights

Slovenia to Italy

Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

Affected volume in MW / hour for each concerned period :

Slovenia to Italy

30/03/2020

01:00 – 02:00 362 MW

02:00 – 03:00 362 MW

03:00 – 04:00 362 MW

04:00 – 05:00 362 MW

05:00 – 06:00 362 MW

06:00 – 07:00 362 MW

07:00 – 08:00 362 MW

08:00 – 09:00 362 MW

09:00 – 10:00 362 MW

10:00 – 11:00 362 MW

11:00 – 12:00 362 MW

12:00 – 13:00 362 MW

13:00 – 14:00 362 MW

14:00 – 15:00 362 MW

15:00 – 16:00 362 MW

16:00 – 17:00 362 MW

17:00 – 18:00 362 MW

Amount of LTTR remaining after curtailment :

Slovenia to Italy

30/03/2020

01:00 – 02:00 184 MW

02:00 – 03:00 184 MW

03:00 – 04:00 184 MW

04:00 – 05:00 184 MW

05:00 – 06:00 258 MW

06:00 – 07:00 258 MW

07:00 – 08:00 279 MW

08:00 – 09:00 279 MW

09:00 – 10:00 279 MW

10:00 – 11:00 300 MW

11:00 – 12:00 300 MW

12:00 – 13:00 300 MW

13:00 – 14:00 300 MW

14:00 – 15:00 300 MW

15:00 – 16:00 300 MW

16:00 – 17:00 300 MW

17:00 – 18:00 300 MW


Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Voltage stability issue on the Italian Electrical system.

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.