[CWE Flow-Based Market Coupling] Adaption of CBCO list of Amprion and TenneT DE
Published:
Dear Market Participants,
Amprion and TenneT DE would like to inform about a small adaption of the CBCO list used for the CWE Flowbased Market Coupling.
Due to the addition of a new substation, the line between Ohlensehlen and Wehrendorf will be converted to a tripod Ohlensehlen - Wehrendorf - St. Hülfe
Accordingly, the CBCO list will be updated.
As this is not a change with a significant impact on the input of the Flowbased calculation, no SPAIC was performed.
The change will be active from Business Day 05/07/2019 onwards.
We hope to have informed you sufficiently and in due time.
Best regards
Amprion and TenneT DE