[CWE Flow-Based Market Coupling] Light SPAIC publication - Outage Meeden-Diele
Dear market participants,
TenneT is planning two outages on the 380 kV Meeden-Diele interconnector (one for each of the parallel circuits). The first outage is currently planned for early March; the second outage is, at the moment, planned directly after the first outage. The exact dates can be found on https://www.tennet.eu/electricity-market/transparencypages/urgent-market-messages-planned-maintenance-nl/.
To assess the impact of this outage on cross-border capacity, a so-called Light SPAIC was performed. For seven reference days from the period Jan 13 – Feb 9, 2020, the flow-based parameters were recalculated with the outage applied.
The enclosed datasets include the flow-based parameters and the list of selected reference days with their main features. Please see the Cover Note for a description of the datasets.
Best regards,
TenneT TSO B.V.