Capacity Curtailment on the DE-NL border for delivery day 03/01/2020

Published:

TSO(s): TenneT TSO B.V.

Identification of affected Long Term Transmission Rights

Germany -> Netherlands

Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation

Affected volume in MW / hour for each concerned period :

03/01/2020

00:00 – 01:00 1081 MW

23:00 – 24:00 1081 MW

Amount of LTTR remaining after curtailment :

03/01/2020

00:00 – 01:00 808 MW

23:00 – 24:00 1060 MW

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).