Capacity Curtailment from Italy to Austria for delivery dates 03, 04, 05 and 06 of November 2018

Published:

Dear Market Participants,

The long-term allocated capacity for delivery dates 03, 04, 05 and 06 of November 2018 on the corridor from Italy to Austria has been curtailed to ensure operation remains within Operational Security Limits.

IT>AT – 03.11.2018:
From position 1 to position 7 reduced to 43 MW
From position 8 to position 23 reduced to 12 MW
On position 24 reduced to 43 MW

IT>AT – 04.11.2018:
From position 1 to position 24 reduced to 43 MW

IT>AT – 05.11.2018:
From position 1 to position 7 reduced to 43 MW
From position 8 to position 23 reduced to 12 MW
On position 24 reduced to 43 MW

IT>AT – 06.11.2018:
From position 1 to position 7 reduced to 43 MW
From position 8 to position 23 reduced to 12 MW
On position 24 reduced to 43 MW

Best regards,

Operations Team

Capacity Allocation

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Image removed.

Attachments