Capacity Curtailment on the FR-IT border for 28th of July
1. TSO(s) *: TERNA
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
France to Italy
28/07/2020
00:00 – 01:00 2051 MW
01:00 – 02:00 2051 MW
02:00 – 03:00 2051 MW
03:00 – 04:00 2051 MW
04:00 – 05:00 2051 MW
05:00 – 06:00 2051 MW
06:00 – 07:00 2051 MW
5. Amount of LTTR remaining after curtailment:
France to Italy
28/07/2020
00:00 – 01:00 1971 MW
01:00 – 02:00 1971 MW
02:00 – 03:00 1971 MW
03:00 – 04:00 1971 MW
04:00 – 05:00 1971 MW
05:00 – 06:00 1971 MW
06:00 – 07:00 1971 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Voltage stability issue on the Italian Electrical system.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
Kind regards,
Gabriele ARNOLDI
Capacity Allocation Specialist
JAO S.A.
2 rue de Bitbourg
L-1273 Luxembourg-Hamm
T. +352 27 62 38 38
Visit us at www.jao.eu
Follow us on LinkedIn
Servicing TSOs and facilitating electricity markets since 2008