The long-term allocated capacities for delivery date 02/01/2019 on the corridor from Austria to Italy and from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.

AT>IT:

From position 1 to position 3 was reduced to 176 MWs

From position 4 to position 5 was reduced to 178 MWs

FR>IT:

From position 1 to position 3 was reduced to 1736 MWs

From position 4 to position 5 was reduced to 1854 MWs

On position 6 was reduced to 2409 MWs

On position 24 was reduced to 2379 MWs

Please consider the latest version of the programming authorizations.

Kind regards,