Capacity Curtailment on the Spain-France border for delivery day 28/02/2020

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 28/02/2020 on the corridor from Spain to France have been curtailed to ensure operation remains within Operational Security Limits.

ES>FR


On position 1 it was reduced to 1531MW
From position 8 to 11 it was reduced to 1531MW
From position 12 to 18 it was reduced to 1477MW
From position 19 to 24 it was reduced to 1531MW

Please consider the latest version of the programming authorizations.

Best regards,
Operations Team