Capacity Curtailment from France to Italy for delivery date 15/11/2018

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 15/11/2018 on the corridors from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT:

On position 7 it was reduced to 2271 MW

From position 8 to position 10 it was reduced to 1997 MW

From position 11 to position 12 it was reduced to 1980 MW

From position 13 to position 15 it was reduced to 1945 MW

From position 16 to position 17 it was reduced to 1980 MW

On position 18 it was reduced to 2327 MW


Please consider the latest version of the programming authorizations.

Best Regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Image removed.

Attachments
image002.jpg