Dear market participants,

TenneT would like to inform you about the results of a performed SPAIC analysis for an upcoming change in grid topology. The 380 kV circuit Borssele – Geertruidenberg Z will be looped into the Rilland 380 kV substation, creating two new circuits: Borssele – Rilland Z and Rilland – Geertruidenberg Z. The new configuration will become operational in mid-May.

The enclosed documents provide the results of the performed SPAIC analysis for the reference period. More details about the SPAIC analysis can be found in the cover note of the SPAIC.

Best regards,

TenneT TSO B.V.