Capacity Curtailment on FR-IT and CH-IT borders for delivery day 04/10/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 04/10/2019 on the corridor from France to Italy and Switzerland to Italy has been curtailed to ensure operation remains within Operational Security Limits.

FR>IT

From position 8 to 12 reduced to 2070 MW

From position 13 to 15 reduced to 2133 MW

CH>IT:

Position 8 reduced by 1%

From position 9 to 12 reduced by 22%

From position 13 to 15 reduced by 19%

From position 16 to 18 reduced by 3%

On positions 19 and 20 reduced by 1%

Please consider the latest version of the programming authorizations.

Best regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Image removed.

Attachments
image003.jpg