Capacity Curtailment on the IF1-GB-FR border for delivery day 19/08/2020

Published:

TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

Identification of affected Long Term Transmission Rights

IFA GB>FR

Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

Affected volume in MW / hour for each concerned period:

19/08/2020

09:00 – 10:00 1699 MW

10:00 – 11:00 1699 MW

11:00 – 12:00 1699 MW

12:00 – 13:00 1699 MW

13:00 – 14:00 1699 MW

14:00 – 15:00 1699 MW

15:00 – 16:00 1699 MW

16:00 – 17:00 1699 MW

Amount of LTTR remaining after curtailment:

19/08/2020

09:00 – 10:00 1500 MW

10:00 – 11:00 1500 MW

11:00 – 12:00 1500 MW

12:00 – 13:00 1500 MW

13:00 – 14:00 1500 MW

14:00 – 15:00 1500 MW

15:00 – 16:00 1500 MW

16:00 – 17:00 1500 MW

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to planned maintenance