Capacity Curtailment on the FR-IT, SI-IT and CH-IT borders for delivery day 01/01/2020

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 01/01/2020 on the corridor from France to Italy, Slovenia to Italy and Switzerland to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT

On position 11 it was reduced to 836 MW

On position 12 it was reduced to 851 MW

On position 13 it was reduced to 874 MW

On position 14 it was reduced to 798 MW

On position 15 it was reduced to 907 MW

SI>IT:

On position 11 it was reduced to 161 MW

On position 12 it was reduced to 163 MW

On position 13 it was reduced to 167 MW

On position 14 it was reduced to 150 MW

On position 15 it was reduced to 173 MW

CH>IT

On position 11 it was reduced by 9%

On position 12 it was reduced by 6%

On position 13 it was reduced by 2%

On position 14 it was reduced by 5%

Please consider the latest version of the programming authorizations.

Best regards,

Operations TEAM