Update on planned outage between Germany and Poland during November and December
Dear Market Participants,
Due to shortening of planned period for construction works rerouting both circuits of the line Mikułowa-Hagenwerder (circuit II - 567 and circuit I - 568) the period announced by the statement on 12th of November 2018 of no physical transmission capacity between DE and PL after update are:
· 15.11 – 27.11.2018
· 04.12 – 06.12.2018
During these days any capacity offered on the 50Hertz technical profile (50Hertz-PL/CZ) can only be auctioned between 50Hertz and Czech Republic. Analogically, any capacity offered on the PSE technical profile (PL-DE/CZ/SK) can only be auctioned between Poland - Czech Republic and Poland - Slovakia. Therefore, placing any bids referring to the capacity on the German-Polish commercial profile will be blocked for this time period.
Best regards,
Operations Team
JAO S.A.
2 rue de Bitbourg
L-1273 Luxembourg-Hamm
T. +352 27 62 38 38