Update on planned outage between Germany and Poland during November and December

Published:

Dear Market Participants,

Due to shortening of planned period for construction works rerouting both circuits of the line Mikułowa-Hagenwerder (circuit II - 567 and circuit I - 568) the period announced by the statement on 12th of November 2018 of no physical transmission capacity between DE and PL after update are:

· 15.11 – 27.11.2018

· 04.12 – 06.12.2018

During these days any capacity offered on the 50Hertz technical profile (50Hertz-PL/CZ) can only be auctioned between 50Hertz and Czech Republic. Analogically, any capacity offered on the PSE technical profile (PL-DE/CZ/SK) can only be auctioned between Poland - Czech Republic and Poland - Slovakia. Therefore, placing any bids referring to the capacity on the German-Polish commercial profile will be blocked for this time period.

Best regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38