Capacity Curtailment on the DE-AT border for delivery day 13/06/2020
TSO(s) *:
APG
Identification of affected Long Term Transmission Rights
DE-AT
Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
Affected volume in MW / hour for each concerned period :
13/06/2020
00:00 – 01:00 4820 MW
01:00 – 02:00 4820 MW
02:00 – 03:00 4820 MW
03:00 - 04:00 4820 MW
04:00 – 05:00 4820 MW
05:00 – 06:00 4820 MW
06:00 – 07:00 4820 MW
07:00 – 08:00 4820 MW
08:00 – 09:00 4820 MW
09:00 – 10:00 4820 MW
10:00 – 11:00 4820 MW
11:00 - 12:00 4820 MW
12:00 – 13:00 4820 MW
13:00 – 14:00 4820 MW
14:00 – 15:00 4820 MW
15:00 – 16:00 4820 MW
16:00 – 17:00 4820 MW
17:00 - 18:00 4820 MW
18:00 – 19:00 4820 MW
19:00 – 20:00 4820 MW
20:00 – 21:00 4820 MW
21:00 – 22:00 4820 MW
22:00 – 23:00 4820 MW
23:00 - 24:00 4820 MW
Amount of LTTR remaining after curtailment :
13/06/2020
00:00 – 01:00 4819 MW
01:00 – 02:00 4819 MW
02:00 – 03:00 4819 MW
03:00 - 04:00 4819 MW
04:00 – 05:00 4819 MW
05:00 – 06:00 4819 MW
06:00 – 07:00 4819 MW
07:00 – 08:00 4819 MW
08:00 – 09:00 4819 MW
09:00 – 10:00 4819 MW
10:00 – 11:00 4819 MW
11:00 - 12:00 4819 MW
12:00 – 13:00 4819 MW
13:00 – 14:00 4819 MW
14:00 – 15:00 4819 MW
15:00 – 16:00 4819 MW
16:00 – 17:00 4819 MW
17:00 - 18:00 4819 MW
18:00 – 19:00 4819 MW
19:00 – 20:00 4819 MW
20:00 – 21:00 4819 MW
21:00 – 22:00 4819 MW
22:00 – 23:00 4819 MW
23:00 - 24:00 4819 MW
Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all remedial actions provided by the TSOs are already considered by the CCC in the calculation.