Capacity Curtailment on the FR-IT borders for delivery day 19/04/2020
1. TSO(s) *: TERNA
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
France to Italy
19/04/2020
§ 05:00 – 06:00 310 MW
§ 06:00 – 07:00 310 MW
§ 07:00 – 08:00 310 MW
§ 08:00 – 09:00 310 MW
§ 09:00 – 10:00 310 MW
§ 10:00 – 11:00 310 MW
§ 11:00 – 12:00 310 MW
§ 12:00 –13:00 310 MW
§ 13:00 – 14:00 310 MW
§ 14:00 -- 15:00 310 MW
§ 15:00 –16:00 310 MW
§ 16:00 – 17:00 310 MW
§ 17:00 –18:00 310 MW
5. Amount of LTTR remaining after curtailment :
France to Italy
19/04/2020
§ 05:00 – 06:00 0 MW
§ 06:00 – 07:00 0 MW
§ 07:00 – 08:00 0 MW
§ 08:00 – 09:00 0 MW
§ 09:00 – 10:00 0 MW
§ 10:00 – 11:00 0 MW
§ 11:00 – 12:00 0 MW
§ 12:00 –13:00 0 MW
§ 13:00 – 14:00 0 MW
§ 14:00 -- 15:00 0 MW
§ 15:00 –16:00 0 MW
§ 16:00 – 17:00 0 MW
§ 17:00 –18:00 293 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:Voltage stability issue on the Italian Electrical system.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.