Capacity Curtailment on the FR-IT border for delivery day 12/09/2020

Published:

1.       TSO(s) *: TERNA, RTE, APG, Swissgrid, ELES

2.       Identification of affected Long Term Transmission Rights

          France to Italy

3.       Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

4. Affected volume in MW / hour for each concerned period:

France to Italy

12/09/2020 

 

00:00 – 01:00  2051 MW

01:00 – 02:00  2051 MW

02:00 – 03:00  2051 MW

03:00 – 04:00  2051 MW

04:00 – 05:00  2051 MW

05:00 – 06:00  2051 MW

06:00 – 07:00  2051 MW

07:00 – 08:00  2051 MW

08:00 – 09:00  2051 MW

09:00 – 10:00  2051 MW

10:00 – 11:00  2051 MW

11:00 – 12:00  2051 MW

12:00 – 13:00  2051 MW

13:00 – 14:00  2051 MW

14:00 – 15:00  2051 MW

15:00 – 16:00  2051 MW

16:00 – 17:00  2051 MW

17:00 – 18:00  2051 MW

18:00 – 19:00  2051 MW

19:00 – 20:00  2051 MW

20:00 – 21:00  2051 MW

21:00 – 22:00  2051 MW

22:00 – 23:00  2051 MW

23:00 – 24:00  2051 MW

 

5. Amount of LTTR remaining after curtailment:

France to Italy

12/09/2020 

 

00:00 – 01:00  2051 MW

01:00 – 02:00  2051 MW

02:00 – 03:00  2051 MW

03:00 – 04:00  1853 MW

04:00 – 05:00  1853 MW

05:00 – 06:00  1853 MW

06:00 – 07:00  1853 MW

07:00 – 08:00  2051 MW

08:00 – 09:00  2051 MW

09:00 – 10:00  2051 MW

10:00 – 11:00  2051 MW

11:00 – 12:00  2051 MW

12:00 – 13:00  2051 MW

13:00 – 14:00  2051 MW

14:00 – 15:00  2051 MW

15:00 – 16:00  2051 MW

16:00 – 17:00  2051 MW

17:00 – 18:00  2051 MW

18:00 – 19:00  2051 MW

19:00 – 20:00  2051 MW

20:00 – 21:00  2051 MW

21:00 – 22:00  2051 MW

22:00 – 23:00  2051 MW

23:00 – 24:00  2051 MW

            

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *: 

          Violation on Divaca-Redipuglia

          

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

          During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation