Capacity Curtailment on the FR-IT border for delivery day 17/09/2020

Published:

1. TSO(s) *: TERNA; RTE, SWISSGRID; APG; ELES

 

2. Identification of affected Long Term Transmission Rights

France to Italy

 

3. Triggering event :

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

4. Affected volume in MW / hour for each concerned period :

 

France to Italy

 

17/09/2020  

18:00 – 19:00  2051 MW

19:00 – 20:00  2051 MW

20:00 – 21:00  2051 MW

23:00 – 24:00  2051 MW

 

 

 

5. Amount of LTTR remaining after curtailment :

 

France to Italy

 

17/09/2020  

18:00 – 19:00  1949 MW

19:00 – 20:00  1949 MW

20:00 – 21:00  1949 MW

23:00 – 24:00  1947 MW

 

<6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

              Reduction due to expected overloads on 380-kV-Fiorano-Robbia

              During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation