Capacity Curtailment on the FR-IT border for delivery day 23/09/2020

Published:

1.      TSO(s) *:  Swissgrid

2.       Identification of affected Long Term Transmission Rights

          France to Italy

3.       Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

4.       Affected volume in MW / hour for each concerned period:

France to Italy

23/09/2020 

 

00:00 – 01:00  2051 MW

01:00 – 02:00  2051 MW

02:00 – 03:00  2051 MW

03:00 – 04:00  2051 MW

04:00 – 05:00  2051 MW

05:00 – 06:00  2051 MW

06:00 – 07:00  2051 MW

 

5.       Amount of LTTR remaining after curtailment:

France to Italy

23/09/2020 

 

00:00 – 01:00  1848 MW

01:00 – 02:00  1848 MW

02:00 – 03:00  1848 MW

03:00 – 04:00  1950 MW

04:00 – 05:00 1950 MW

05:00 – 06:00  1950 MW

06:00 – 07:00  1950 MW

            

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

          For period

00:00 – 01:00  1848 MW

01:00 – 02:00  1848 MW

02:00 – 03:00  1848 MW

Reduction due to the following overloaded element(s): 380kV Fiorano - Robbia (N-1 SOAZZA-BULCIAGO);380kV Sils - Soazza (N-1 ROBBIA-S.FIORANO);380kV Lavorgo - Musignano (N-1 ROBBIA-S.FIORANO);380kV Robbia - Y/Punt (N-2 PRADELLA-ROBBIA_PROV + FILISUR-ROBBIA);380kV Bucliago - Soazza (N-1 ROBBIA-S.FIORANO);220kV Riddes - Valpelline (N-1 AVISE-RIDDES)

          For period

03:00 – 04:00  1950 MW

04:00 – 05:00 1950 MW

05:00 – 06:00  1950 MW

06:00 – 07:00  1950 MW

Reduction due to the following overloaded element(s): 380kV Fiorano - Robbia (N-1 SOAZZA-BULCIAGO);380kV Lavorgo - Musignano (N-1 ROBBIA-S.FIORANO);380kV Sils - Soazza (N-1 ROBBIA-S.FIORANO);380kV Robbia - Y/Punt (N-2 PRADELLA-ROBBIA_PROV + FILISUR-ROBBIA);380kV Bucliago - Soazza (N-1 ROBBIA-S.FIORANO)

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

           During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation