Capacity Curtailment on the FR-IT border for delivery day 05/10/2020
1. TSO(s) *:
Swissgrid
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
France to Italy
05/10/2020
12:00 – 13:00 2480 MW
13:00 – 14:00 2480 MW
14:00 – 15:00 2480 MW
5. Amount of LTTR remaining after curtailment:
France to Italy
05/10/2020
12:00 – 13:00 2419 MW
13:00 – 14:00 2419 MW
14:00 – 15:00 2419 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Reduction due to the following overloaded element(s): 380kV Pradella - Y/Punt (N-2 DIVACA-REDIPUGLIA + DIVACA-PADRICIANO)
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
Questo messaggio (allegati eventuali compresi) contiene informazioni del Gruppo Terna che devono essere utilizzate esclusivamente dai destinatari in relazione alle finalità per le quali sono state inviate. È vietata qualsiasi forma di divulgazione senza l’esplicito consenso di Terna. Qualora questa e-mail sia stata ricevuta per errore, si prega di provvedere alla distruzione dell’intero messaggio e di informare tempestivamente il mittente. Grazie.
This email (and any files transmitted with it) includes Terna Group information and is intended solely for the use of the recipients to whom it is addressed. Please note that disclosing the contents of this email is strictly prohibited without Terna’s express consent. Please notify the sender immediately if you have received this e-mail by mistake and delete this e-mail from your system. Thank you.