Capacity Curtailment on the DK<>NL border for delivery day 14/11/2020

Published:

1.       TSO(s): TenneT TSO B.V.

 

2.       Identification of affected Long Term Transmission Rights

Denmark <-> Netherlands
 

3.       Triggering event :

 

☐Curtailment to ensure operation remains within Operational Security Limits

☒Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

4.       Affected volume in MW / hour for each concerned period :

14/11/2020:

Denmark -> Netherlands:
        • 00:00 - 23:59: 700 MW

Netherlands -> Denmark:
        • 00:00 - 23:59: 700 MW
 

5.       Amount of LTTR remaining after curtailment :

14/11/2020:

Denmark -> Netherlands:
        • 00:00 - 23:59: 0 MW

Netherlands -> Denmark:
        • 00:00 - 23:59: 0 MW
 

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

 

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).

 

Best regards,

 

Operations TEAM

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Visit us at www.jao.eu

Follow us on LinkedIn

 

 
JAO is celebrating the 5th anniversary of the

merger between CAO GMbH and CASC.EU S.A.

The company has been facilitating the European electricity market

since 2008 and continues to strive for a fairer and stronger market