Capacity Curtailment on the DK2-DE border for delivery period from 29/11/2020 until 04/12/2020
TSO(s) *:
50Hertz and Energinet
Identification of affected Long Term Transmission Rights
DK2-DE/Kontek.
Triggering event :
Cable outage.
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
Affected volume in MW / hour for each concerned period :
120 MW Yearly for each hour over the whole curtailment period from 22-10-2020 until 04-12-2020.
120 MW Monthly for each hour over the periods from 22-10-2020 until 31-10-2020 and from 01-12-2020 until 04-12-2020, respectively.
[Note: For the time period from 01-11-2020 until 30-11-2020, no monthly capacities were offered and allocated to the market.]
Amount of LTTR remaining after curtailment :
0
Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
There is no alternative to the curtailment of the affected LTTRs as the border DK2-DE is formed exclusively by KONTEK and KONTEK is completely unavailable due to an forced outage.
Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
cf. answer to point 6..