Capacity Curtailment on the D2-DE border for delivery days 05/12/2020 to 14/12/2020

Published:
TSO(s) *:

50Hertz and Energinet

 

Identification of affected Long Term Transmission Rights

DK2-DE/Kontek.

 

Triggering event :

Cable outage.

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

Affected volume in MW / hour for each concerned period :

120 MW Yearly for each hour over the whole curtailment period from 22-10-2020 until 14-12-2020.   

120 MW Monthly for each hour over the periods from 22-10-2020 until 31-10-2020 and from 01-12-2020 until 14-12-2020, respectively.

[Note: For the time period from 01-11-2020 until 30-11-2020, no monthly capacities were offered and allocated to the market.]

 

 

Amount of LTTR remaining after curtailment :

0

 

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

There is no alternative to the curtailment of the affected LTTRs as the border DK2-DE is formed exclusively by KONTEK and KONTEK is completely unavailable due to an forced outage.

 

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

cf. answer to point 6..

 

 

 

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication