Capacity Curtailment on the GR<>IT border for delivery day 03/03/2021

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 03/03/2021 on the corridor from Greece to Italy have been curtailed to ensure operation remains within Operational Security Limits.

1.       Affected volume in MW / hour for each concerned period :

Greece <-> Italy

 

03/03/2021 – 03/03/2021 

 

 

§  09:00 - 10:00      500 MW             

§  10:00 - 11:00      500 MW             

§  11:00 - 12:00      500 MW

§  12:00 – 13:00    500 MW              

 

 

 

2.       Amount of LTTR remaining after curtailment :

03/03/2021 – 03/03/2021 

           

§  09:00 - 10:00      0 MW  

§  10:00 - 11:00      0 MW  

§  11:00 - 12:00      0 MW

§  12:00 - 13:00      0 MW

 

Please consider the latest version of the programming authorizations.

Best regards,
Operations Team