Capacity Curtailment on the AT-IT border for delivery day 07/03/2021

Published:

1.       TSO(s) *: 

2.       Identification of affected Long Term Transmission Rights

          Austria to Italy

3.       Triggering event:

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation

4.       Affected volume in MW / hour for each concerned period:

         Austria to Italy

07/03/2021 

•          18:00 - 19:00 90 MW

5.       Amount of LTTR remaining after curtailment:

         Austria to Italy

07/03/2021 

•          18:00 - 19:00 78 MW

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

         

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?