Capacity Curtailment on the AT-IT border for delivery day 07/03/2021
1. TSO(s) *:
2. Identification of affected Long Term Transmission Rights
Austria to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Austria to Italy
07/03/2021
• 18:00 - 19:00 90 MW
5. Amount of LTTR remaining after curtailment:
Austria to Italy
07/03/2021
• 18:00 - 19:00 78 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?