Capacity Curtailment on the BDL GB<>NL border for delivery days 11/03/2021 to 22/04/2021
1. TSO(s) *
BritNed Development Limited
Identification of affected Long Term Transmission Rights
BDL GB-NL
BDL NL-GB
Triggering event:
Curtailment due to emergency situation
Affected volume in MW / hour for each concerned period :
BDL GB-NL 11.03.2021 00:00 – 22.04.2021 00:00 - 828 MW
BDL NL-GB 11.03.2021 00:00 – 22.04.2021 00:00 - 941 MW
Amount of LTTR remaining after curtailment :
BDL GB-NL 11.03.2021 00:00 – 22.04.2021 00:00 - 0 MW
BDL NL-GB 11.03.2021 00:00 – 22.04.2021 00:00 - 0 MW
5. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
N/A
6.
Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *
Early investigation indicates a cable fault