Capacity Curtailment on the FR-IT border for delivery day 03/04/2021

Published:

1. TSO(s) *: APG – ELE – RTE – TERNA - SWG

2. Identification of affected Long Term Transmission Rights

France to Italy

3. Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

France to Italy

03/04/2021  

 

00:00 – 01:00  873 MW

01:00 – 02:00  873 MW

02:00 – 03:00  873 MW

03:00 – 04:00  873 MW

04:00 – 05:00  873 MW

05:00 – 06:00  873 MW

06:00 – 07:00  873 MW

07:00 – 08:00  873 MW

08:00 – 09:00  873 MW

09:00 – 10:00  873 MW

10:00 – 11:00  873 MW

11:00 – 12:00  873 MW

12:00 – 13:00  873 MW

13:00 – 14:00  873 MW

14:00 – 15:00  873 MW

15:00 – 16:00  873 MW

16:00 – 17:00  873 MW

17:00 – 18:00  873 MW

18:00 – 19:00  873 MW

19:00 – 20:00  873 MW

20:00 – 21:00  873 MW

21:00 – 22:00  873 MW

22:00 – 23:00  873 MW

23:00 – 24:00  873 MW 

 

5. Amount of LTTR remaining after curtailment:

France to Italy

03/04/2021  

  Due to SWG

09:00 – 10:00  647 MW

10:00 – 11:00  247 MW

11:00 – 12:00  247 MW

15:00 – 16:00  235 MW

16:00 – 17:00  235 MW

17:00 – 18:00  226 MW

 

Due to All

12:00 – 13:00  248 MW

13:00 – 14:00  248 MW

14:00 – 15:00  248 MW

18:00 – 19:00  184 MW

19:00 – 20:00  231 MW

20:00 – 21:00  231 MW

21:00 – 22:00  231 MW

22:00 – 23:00  231 MW

23:00 – 24:00  0 MW 

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

  Period of curtailment due to SWG: 380kV Sils – Soazza

Period of curtailment due to All: Soverzene - lienz

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

 

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.