Capacity Curtailment on the SI-IT border for delivery day 03/04/2021
1. TSO(s) *: APG – ELE – RTE – TERNA - SWG
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Slovenia to Italy
03/04/2021
00:00 – 01:00 363MW
01:00 – 02:00 363MW
02:00 – 03:00 363MW
03:00 – 04:00 363MW
04:00 – 05:00 363MW
05:00 – 06:00 363MW
06:00 – 07:00 363MW
07:00 – 08:00 363MW
08:00 – 09:00 363MW
09:00 – 10:00 363MW
10:00 – 11:00 363MW
11:00 – 12:00 363MW
12:00 – 13:00 363MW
13:00 – 14:00 363MW
14:00 – 15:00 363MW
15:00 – 16:00 363MW
16:00 – 17:00 363MW
17:00 – 18:00 363MW
18:00 – 19:00 363MW
19:00 – 20:00 363MW
20:00 – 21:00 363MW
21:00 – 22:00 363MW
22:00 – 23:00 363MW
23:00 – 24:00 363MW
5. Amount of LTTR remaining after curtailment:
Slovenia to Italy
03/04/2021
Due to SWG
08:00 – 09:00 295MW
09:00 – 10:00 139MW
10:00 – 11:00 50MW
11:00 – 12:00 50MW
15:00 – 16:00 46MW
16:00 – 17:00 46MW
17:00 – 18:00 43MW
Due to All
12:00 – 13:00 50MW
13:00 – 14:00 50MW
14:00 – 15:00 50MW
18:00 – 19:00 38MW
19:00 – 20:00 68MW
20:00 – 21:00 68MW
21:00 – 22:00 68MW
22:00 – 23:00 68MW
23:00 – 24:00 0MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Period of curtailment due to SWG: 380kV Sils – Soazza
Period of curtailment due to All: Soverzene - lienz
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.