Capacity Curtailment on the DE-NL border for delivery day 08/04/2021
1. TSO(s): TenneT TSO B.V.
2. Identification of affected Long Term Transmission Rights
Germany -> Netherlands
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
08/04/2021:
Germany -> Netherlands:
• 00:00 - 01:00: 1080 MW
• 01:00 - 02:00: 1080 MW
• 02:00 - 03:00: 1080 MW
• 03:00 - 04:00: 1080 MW
• 04:00 - 05:00: 1080 MW
• 05:00 - 06:00: 1080 MW
• 15:00 - 16:00: 1080 MW
• 18:00 - 19:00: 1080 MW
• 19:00 - 20:00: 1080 MW
• 20:00 - 21:00: 1080 MW
• 21:00 - 22:00: 1080 MW
5. Amount of LTTR remaining after curtailment :
08/04/2021:
Germany -> Netherlands:
• 00:00 - 01:00: 480 MW
• 01:00 - 02:00: 480 MW
• 02:00 - 03:00: 480 MW
• 03:00 - 04:00: 480 MW
• 04:00 - 05:00: 480 MW
• 05:00 - 06:00: 480 MW
• 15:00 - 16:00: 480 MW
• 18:00 - 19:00: 480 MW
• 19:00 - 20:00: 480 MW
• 20:00 - 21:00: 480 MW
• 21:00 - 22:00: 480 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).