Capacity Curtailment on the NL-BE border for delivery day 12/04/2021
1. TSO(s): TenneT TSO B.V.
2. Identification of affected Long Term Transmission Rights
Netherlands -> Belgium
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
12/04/2021:
Netherlands -> Belgium:
• 09:00 - 10:00: 692 MW
• 10:00 - 11:00: 692 MW
5. Amount of LTTR remaining after curtailment :
12/04/2021:
Netherlands -> Belgium:
• 09:00 - 10:00: 519 MW
• 10:00 - 11:00: 617 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).
Best regards,
Operations Team