Capacity Curtailment on the CH-IT border for delivery day 07/05/2022

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 07/05/2022 on the corridor from Switzerland to Italy have been curtailed to ensure operation remains within Operational Security Limits.

CH>IT

From the position 1 to position 3 it was reduced by 8%
From the position 4 to position 7 it was reduced by 10%
From the position 10 to position 14 it was reduced by 1%
On the position 15 was reduced by 3%
From the position 16 to position 17 it was reduced by 11%

Please consider the latest version of the programming authorizations.

Best regards,

Operations Team