Capacity Curtailment on the BE-NL border for delivery day 20/06/2022

Published:

1.         TSO(s):

TenneT TSO B.V.

2.         Identification of affected Long Term Transmission Rights

Belgium -> Netherlands

3.         Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

☒Adjusted because of expected violation of operational security

☒Adjusted because already considered remedial actions are assessed as not sufficient

4.         Affected volume in MW / hour for each concerned period :

20/06/2022:

Belgium -> Netherlands:

20:00 – 21:00  619 MW

5. Amount of LTTR remaining after curtailment :

20/06/2022:

Germany -> Netherlands:

20:00 – 21:00  158 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).