Capacity Curtailment on the SI-IT border for delivery day 23/08/2022

Published:

TSO(s) *:

TERNA, RTE, Swissgrid, APG, ELES

Identification of affected Long Term Transmission Rights
SI-IT

Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation

Affected volume in MW / hour for each concerned period :
23/08/2022


23:00 – 24:00 389 MW


Amount of LTTR remaining after curtailment :
23/08/2022


23:00 – 24:00 358 MW
 

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Violation on Lienz – Soverzene due to Critical outage DIVACA-REDIPUGLIA/DIVACA-PADRICIANO

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation