Capacity Curtailment on the SI-IT border for delivery day 28/08/2022
1. TSO(s) *: TERNA, ELES
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Slovenia to Italy
28/08/2022
21:00 – 22:00 389 MW
22:00 – 23:00 389 MW
23:00 – 24:00 389 MW
5. Amount of LTTR remaining after curtailment:
Slovenia to Italy
28/08/2022
21:00 – 22:00 357 MW
22:00 – 23:00 357 MW
23:00 – 24:00 357 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Voltage stability issue on the Italian Electrical system
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.