Capacity Curtailment on the FR-IT border for delivery 26-01-2023

Published:

1.TSO(s)*:

TERNA, APG, SWISSGRID, ELES, RTE

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

26-01-2023 00:00 - 01:00 2747 MW

26-01-2023 01:00 - 02:00 2747 MW

26-01-2023 02:00 - 03:00 2747 MW

26-01-2023 03:00 - 04:00 2747 MW

26-01-2023 04:00 - 05:00 2747 MW

26-01-2023 05:00 - 06:00 2747 MW

26-01-2023 06:00 - 07:00 2747 MW

5. Amount of LTTR remaining after curtailment:

26-01-2023 00:00 - 01:00 2652 MW

26-01-2023 01:00 - 02:00 2652 MW

26-01-2023 02:00 - 03:00 2652 MW

26-01-2023 03:00 - 04:00 2652 MW

26-01-2023 04:00 - 05:00 2652 MW

26-01-2023 05:00 - 06:00 2652 MW

26-01-2023 06:00 - 07:00 2652 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation on the following elements: Lienz-Soverzene

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC calculation