Capacity Curtailment on the DE-NL border for delivery 10-02-2023

Published:

1. TSO(s)*:

JAO

2. Identification of affected Long Term Transmission Rights:

DE-NL

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

10-02-2023 16:00 - 17:00 1081 MW

5. Amount of LTTR remaining after curtailment:

10-02-2023 16:00 - 17:00 456 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).