Capacity Curtailment on the NL-BE border for delivery 10-02-2023
1. TSO(s)*:
TenneT_NL
2. Identification of affected Long Term Transmission Rights:
NL-BE
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
10-02-2023 16:00 - 17:00 619 MW
…
10-02-2023 18:00 - 19:00 619 MW
5. Amount of LTTR remaining after curtailment:
10-02-2023 16:00 - 17:00 152 MW
…
10-02-2023 18:00 - 19:00 152 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).