Capacity Curtailment on the ES-FR border for delivery 13-02-2023
Published:
1. TSO(s) :
RTE, REE
2. Identification of affected Long Term Transmission Rights
ES->FR
3. Triggering event :
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period :
13/02/2023
06:00-07:00 1660.0 MW
07:00-08:00 1660.0 MW
08:00-09:00 1660.0 MW
09:00-10:00 1660.0 MW
10:00-11:00 1660.0 MW
5. Amount of LTTR remaining after curtailment :
13/02/2023
06:00-07:00 1650 MW
07:00-08:00 1650 MW
08:00-09:00 1650 MW
09:00-10:00 1650 MW
10:00-11:00 1650 MW
6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :
13/02/2023
06:00-07:00 Network Security
07:00-08:00 Network Security
08:00-09:00 Network Security
09:00-10:00 Network Security
10:00-11:00 Network Security
7. What alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits