Capacity Curtailment on the AT-IT border for delivery 01-03-2023

Published:

1. TSO(s)*:

TERNA

 

 

2. Identification of affected Long Term Transmission Rights:

AT-IT

 

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

 

4. Affected volume in MW / hour for each concerned period:

 

01-03-2023 03:00 - 04:00 456 MW

01-03-2023 04:00 - 05:00 456 MW

01-03-2023 05:00 - 06:00 456 MW

01-03-2023 06:00 - 07:00 456 MW

 

5. Amount of LTTR remaining after curtailment:

 

01-03-2023 03:00 - 04:00 387 MW

01-03-2023 04:00 - 05:00 387 MW

01-03-2023 05:00 - 06:00 387 MW

01-03-2023 06:00 - 07:00 387 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

 

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

 

 

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication