Capacity Curtailment on the AT-IT border for delivery 11-04-2023
1. TSO(s)*: TERNA
2. Identification of affected Long Term Transmission Rights:
AT-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
11-04-2023 00:00 - 01:00 199 MW
11-04-2023 01:00 - 02:00 199 MW
11-04-2023 02:00 - 03:00 199 MW
11-04-2023 03:00 - 04:00 199 MW
11-04-2023 04:00 - 05:00 199 MW
5. Amount of LTTR remaining after curtailment:
11-04-2023 00:00 - 01:00 168 MW
11-04-2023 01:00 - 02:00 161 MW
11-04-2023 02:00 - 03:00 151 MW
11-04-2023 03:00 - 04:00 154 MW
11-04-2023 04:00 - 05:00 161 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.