Capacity Curtailment on the AT-IT border for delivery 06-08-2023
1. TSO(s)*: TERNA
2. Identification of affected Long Term Transmission Rights:
AT-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
06-08-2023 07:00 - 08:00 134 MW
06-08-2023 08:00 - 09:00 134 MW
06-08-2023 09:00 - 10:00 134 MW
06-08-2023 10:00 - 11:00 134 MW
06-08-2023 11:00 - 12:00 134 MW
06-08-2023 12:00 - 13:00 134 MW
06-08-2023 13:00 - 14:00 134 MW
06-08-2023 14:00 - 15:00 134 MW
06-08-2023 15:00 - 16:00 134 MW
06-08-2023 16:00 - 17:00 134 MW
06-08-2023 17:00 - 18:00 134 MW
06-08-2023 18:00 - 19:00 134 MW
5. Amount of LTTR remaining after curtailment:
06-08-2023 07:00 - 08:00 120 MW
06-08-2023 08:00 - 09:00 75 MW
06-08-2023 09:00 - 10:00 26 MW
06-08-2023 10:00 - 11:00 0 MW
06-08-2023 11:00 - 12:00 0 MW
06-08-2023 12:00 - 13:00 0 MW
06-08-2023 13:00 - 14:00 0 MW
06-08-2023 14:00 - 15:00 0 MW
06-08-2023 15:00 - 16:00 0 MW
06-08-2023 16:00 - 17:00 4 MW
06-08-2023 17:00 - 18:00 53 MW
06-08-2023 18:00 - 19:00 102 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.