Capacity Curtailment on the CH-IT border for delivery 09-08-2023

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 09-08-2023 on the corridor CH-IT  have been curtailed to ensure operation remains within Operational Security Limits.

09-08-2023 07:00 - 08:00 was reduced by 3 %

09-08-2023 08:00 - 09:00 was reduced by 9 %

09-08-2023 09:00 - 10:00 was reduced by 5 %

09-08-2023 10:00 - 11:00 was reduced by 5 %

09-08-2023 11:00 - 12:00 was reduced by 5 %

09-08-2023 12:00 - 13:00 was reduced by 9 %

09-08-2023 13:00 - 14:00 was reduced by 9 %

09-08-2023 14:00 - 15:00 was reduced by 9 %

09-08-2023 15:00 - 16:00 was reduced by 6 %

09-08-2023 16:00 - 17:00 was reduced by 6 %

09-08-2023 17:00 - 18:00 was reduced by 5 %

09-08-2023 18:00 - 19:00 was reduced by 6 %

09-08-2023 19:00 - 20:00 was reduced by 3 %

Please consider the latest version of the programming authorizations.

Best regards,