Capacity Curtailment on the FR-IT border for delivery 01-10-2023
1. TSO(s)*:
2. Identification of affected Long Term Transmission Rights:
FR-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
01-10-2023 09:00 - 10:00 2380 MW
01-10-2023 10:00 - 11:00 2380 MW
01-10-2023 11:00 - 12:00 2380 MW
01-10-2023 12:00 - 13:00 2380 MW
01-10-2023 13:00 - 14:00 2380 MW
01-10-2023 14:00 - 15:00 2380 MW
01-10-2023 15:00 - 16:00 2380 MW
01-10-2023 16:00 - 17:00 2380 MW
01-10-2023 17:00 - 18:00 2380 MW
5. Amount of LTTR remaining after curtailment:
01-10-2023 09:00 - 10:00 1898 MW
01-10-2023 10:00 - 11:00 1212 MW
01-10-2023 11:00 - 12:00 576 MW
01-10-2023 12:00 - 13:00 249 MW
01-10-2023 13:00 - 14:00 296 MW
01-10-2023 14:00 - 15:00 382 MW
01-10-2023 15:00 - 16:00 885 MW
01-10-2023 16:00 - 17:00 1564 MW
01-10-2023 17:00 - 18:00 2238 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication