Capacity Curtailment on the FR-IT border for delivery 10-10-2023

Published:

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

10-10-2023 15:00 - 16:00 2380 MW

10-10-2023 16:00 - 17:00 2380 MW

10-10-2023 17:00 - 18:00 2380 MW

5. Amount of LTTR remaining after curtailment:

10-10-2023 15:00 - 16:00 2117 MW

10-10-2023 16:00 - 17:00 2117 MW

10-10-2023 17:00 - 18:00 2117 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication