Capacity Curtailment on the D2-DE border for delivery 22-10-2023 to 31-10-2023

Published:

1. TSO(s):

50Hertz, Energinet

2. Identification of affected Long Term Transmission Rights:

D2-DE

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

00:00 - 01:00 250 MW

01:00 - 02:00 250 MW

02:00 - 03:00 250 MW

03:00 - 04:00 250 MW

04:00 - 05:00 250 MW

05:00 - 06:00 250 MW

06:00 - 07:00 250 MW

07:00 - 08:00 250 MW

08:00 - 09:00 250 MW

09:00 - 10:00 250 MW

10:00 - 11:00 250 MW

11:00 - 12:00 250 MW

12:00 - 13:00 250 MW

13:00 - 14:00 250 MW

14:00 - 15:00 250 MW

15:00 - 16:00 250 MW

16:00 - 17:00 250 MW

17:00 - 18:00 250 MW

18:00 - 19:00 250 MW

19:00 - 20:00 250 MW

20:00 - 21:00 250 MW

21:00 - 22:00 250 MW

22:00 - 23:00 250 MW

23:00 - 24:00 250 MW

5. Amount of LTTR remaining after curtailment:

00:00 - 01:00 58 MW

01:00 - 02:00 58 MW

02:00 - 03:00 58 MW

03:00 - 04:00 58 MW

04:00 - 05:00 58 MW

05:00 - 06:00 58 MW

06:00 - 07:00 58 MW

07:00 - 08:00 58 MW

08:00 - 09:00 58 MW

09:00 - 10:00 58 MW

10:00 - 11:00 58 MW

11:00 - 12:00 58 MW

12:00 - 13:00 58 MW

13:00 - 14:00 58 MW

14:00 - 15:00 58 MW

15:00 - 16:00 58 MW

16:00 - 17:00 58 MW

17:00 - 18:00 58 MW

18:00 - 19:00 58 MW

19:00 - 20:00 58 MW

20:00 - 21:00 58 MW

21:00 - 22:00 58 MW

22:00 - 23:00 58 MW

23:00 - 24:00 58 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:

There is no alternative to the curtailment of the affected LTTRs.

Due to the unplanned outage of Kontek Cable the maximum transmission capacity of the interconnectors on the border DE/LU – DK2 is limited due to the thermal capacity of the remaining grid elements.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?

cf. answer to point 6