Capacity Curtailment on the SI-IT border for delivery 05-11-2023
1. TSO(s):
TERNA
2. Identification of affected Long Term Transmission Rights:
SI-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
05-11-2023 00:00 - 01:00 456 MW
05-11-2023 01:00 - 02:00 456 MW
05-11-2023 02:00 - 03:00 456 MW
05-11-2023 03:00 - 04:00 456 MW
05-11-2023 04:00 - 05:00 456 MW
05-11-2023 05:00 - 06:00 456 MW
05-11-2023 06:00 - 07:00 456 MW
05-11-2023 07:00 - 08:00 456 MW
05-11-2023 08:00 - 09:00 456 MW
05-11-2023 09:00 - 10:00 456 MW
05-11-2023 10:00 - 11:00 456 MW
05-11-2023 11:00 - 12:00 456 MW
05-11-2023 12:00 - 13:00 456 MW
05-11-2023 13:00 - 14:00 456 MW
05-11-2023 14:00 - 15:00 456 MW
05-11-2023 15:00 - 16:00 456 MW
05-11-2023 16:00 - 17:00 456 MW
05-11-2023 17:00 - 18:00 456 MW
05-11-2023 20:00 - 21:00 456 MW
05-11-2023 21:00 - 22:00 456 MW
05-11-2023 22:00 - 23:00 456 MW
05-11-2023 23:00 - 24:00 456 MW
5. Amount of LTTR remaining after curtailment:
05-11-2023 00:00 - 01:00 218 MW
05-11-2023 01:00 - 02:00 141 MW
05-11-2023 02:00 - 03:00 141 MW
05-11-2023 03:00 - 04:00 141 MW
05-11-2023 04:00 - 05:00 141 MW
05-11-2023 05:00 - 06:00 157 MW
05-11-2023 06:00 - 07:00 157 MW
05-11-2023 07:00 - 08:00 151 MW
05-11-2023 08:00 - 09:00 173 MW
05-11-2023 09:00 - 10:00 178 MW
05-11-2023 10:00 - 11:00 141 MW
05-11-2023 11:00 - 12:00 151 MW
05-11-2023 12:00 - 13:00 134 MW
05-11-2023 13:00 - 14:00 118 MW
05-11-2023 14:00 - 15:00 170 MW
05-11-2023 15:00 - 16:00 235 MW
05-11-2023 16:00 - 17:00 313 MW
05-11-2023 17:00 - 18:00 419 MW
05-11-2023 20:00 - 21:00 419 MW
05-11-2023 21:00 - 22:00 406 MW
05-11-2023 22:00 - 23:00 313 MW
05-11-2023 23:00 - 24:00 235 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation