Capacity Curtailment on the SI-IT border for delivery 25-12-2023

Published:

1. TSO(s)*:
TERNA-ELES

2. Identification of affected Long Term Transmission Rights:

SI-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

25-12-2023 00:00 - 01:00 344 MW

25-12-2023 01:00 - 02:00 344 MW

25-12-2023 02:00 - 03:00 344 MW

25-12-2023 03:00 - 04:00 344 MW

25-12-2023 04:00 - 05:00 344 MW

25-12-2023 05:00 - 06:00 344 MW

25-12-2023 06:00 - 07:00 344 MW

25-12-2023 07:00 - 08:00 344 MW

25-12-2023 08:00 - 09:00 344 MW

25-12-2023 09:00 - 10:00 344 MW

25-12-2023 10:00 - 11:00 344 MW

25-12-2023 11:00 - 12:00 344 MW

25-12-2023 12:00 - 13:00 344 MW

25-12-2023 13:00 - 14:00 344 MW

25-12-2023 14:00 - 15:00 344 MW

25-12-2023 15:00 - 16:00 344 MW

25-12-2023 16:00 - 17:00 344 MW

25-12-2023 17:00 - 18:00 344 MW

25-12-2023 18:00 - 19:00 344 MW

25-12-2023 19:00 - 20:00 344 MW

25-12-2023 20:00 - 21:00 344 MW

25-12-2023 21:00 - 22:00 344 MW

25-12-2023 22:00 - 23:00 344 MW

25-12-2023 23:00 - 24:00 344 MW

5. Amount of LTTR remaining after curtailment:

25-12-2023 00:00 - 01:00 166 MW

25-12-2023 01:00 - 02:00 126 MW

25-12-2023 02:00 - 03:00 67 MW

25-12-2023 03:00 - 04:00 52 MW

25-12-2023 04:00 - 05:00 58 MW

25-12-2023 05:00 - 06:00 93 MW

25-12-2023 06:00 - 07:00 139 MW

25-12-2023 07:00 - 08:00 159 MW

25-12-2023 08:00 - 09:00 133 MW

25-12-2023 09:00 - 10:00 133 MW

25-12-2023 10:00 - 11:00 126 MW

25-12-2023 11:00 - 12:00 106 MW

25-12-2023 12:00 - 13:00 106 MW

25-12-2023 13:00 - 14:00 58 MW

25-12-2023 14:00 - 15:00 52 MW

25-12-2023 15:00 - 16:00 106 MW

25-12-2023 16:00 - 17:00 147 MW

25-12-2023 17:00 - 18:00 147 MW

25-12-2023 18:00 - 19:00 147 MW

25-12-2023 19:00 - 20:00 147 MW

25-12-2023 20:00 - 21:00 147 MW

25-12-2023 21:00 - 22:00 151 MW

25-12-2023 22:00 - 23:00 151 MW

25-12-2023 23:00 - 24:00 151 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication