Capacity Curtailment on the CH-IT border for delivery 03-01-2024

Published:

1. TSO(s)*:

SWISSGRID - TERNA

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Estimated duration and affected volume in MW / hour for each concerned period:

03-01-2024 00:00 - 01:00 2602 MW

03-01-2024 01:00 - 02:00 2602 MW

03-01-2024 02:00 - 03:00 2602 MW

03-01-2024 03:00 - 04:00 2602 MW

03-01-2024 04:00 - 05:00 2602 MW

03-01-2024 05:00 - 06:00 2602 MW

03-01-2024 06:00 - 07:00 2602 MW

03-01-2024 07:00 - 08:00 2602 MW

03-01-2024 08:00 - 09:00 3297 MW

03-01-2024 09:00 - 10:00 3297 MW

03-01-2024 10:00 - 11:00 3297 MW

03-01-2024 11:00 - 12:00 3297 MW

03-01-2024 12:00 - 13:00 3297 MW

03-01-2024 13:00 - 14:00 3297 MW

03-01-2024 14:00 - 15:00 3297 MW

03-01-2024 15:00 - 16:00 3297 MW

03-01-2024 16:00 - 17:00 3297 MW

03-01-2024 17:00 - 18:00 3297 MW

03-01-2024 18:00 - 19:00 3297 MW

03-01-2024 19:00 - 20:00 3297 MW

03-01-2024 20:00 - 21:00 2602 MW

03-01-2024 21:00 - 22:00 2602 MW

03-01-2024 22:00 - 23:00 2602 MW

03-01-2024 23:00 - 24:00 2602 MW

5. Estimated duration and amount of LTTR remaining after curtailment:

03-01-2024 00:00 - 01:00 1824 MW

03-01-2024 01:00 - 02:00 1672 MW

03-01-2024 02:00 - 03:00 1438 MW

03-01-2024 03:00 - 04:00 1358 MW

03-01-2024 04:00 - 05:00 1410 MW

03-01-2024 05:00 - 06:00 1438 MW

03-01-2024 06:00 - 07:00 1877 MW

03-01-2024 07:00 - 08:00 1957 MW

03-01-2024 08:00 - 09:00 2046 MW

03-01-2024 09:00 - 10:00 2216 MW

03-01-2024 10:00 - 11:00 2216 MW

03-01-2024 11:00 - 12:00 1968 MW

03-01-2024 12:00 - 13:00 2179 MW

03-01-2024 13:00 - 14:00 2349 MW

03-01-2024 14:00 - 15:00 2445 MW

03-01-2024 15:00 - 16:00 2375 MW

03-01-2024 16:00 - 17:00 2349 MW

03-01-2024 17:00 - 18:00 2445 MW

03-01-2024 18:00 - 19:00 2375 MW

03-01-2024 19:00 - 20:00 2349 MW

03-01-2024 20:00 - 21:00 2392 MW

03-01-2024 21:00 - 22:00 2324 MW

03-01-2024 22:00 - 23:00 2392 MW

03-01-2024 23:00 - 24:00 2286 MW

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication